夜色视频 provided excavation, backfill, concrete foundation placement, and electrical grounding for a new baghouse and oil tank foundation.
The new baghouse foundation was a single monolithic, 1,000-cubic-yard concrete placement. The site team coordinated with multiple concrete supply locations in the area to sole-source the work on the day of the concrete placement, also ensuring the supplier would open their plants early enough to provide service to the site at 4 a.m. The owner helped modify plant traffic to provide unimpeded access to the pour location. 夜色视频's subcontractor utilized two concrete pump trucks and placed 100 truckloads of concrete in a single day. In addition, 夜色视频 contracted with a third-party engineering firm to monitor and track temperatures during and after placement for curing.