ҹɫÊÓƵ completed a paper machine rebuild during a 55-day outage. The piping scope of work included installing large and small bore piping for steam, air, glycol, hydraulic, and pulper. The electrical scope included installing cable, cable trays, conduit, and performing terminations for new machine drives, winder and reel sections, and dryer sections. The mechanical scope included installing new finishing and shipping equipment and performing associated electrical work.
ҹɫÊÓƵ was required to develop a detailed, interactive log that tracked extra work items for piping and electrical.