ҹɫÊÓƵ

Return
Location:
Virginia & North Carolina
Completed:
2019

115 kV Transmission Line Rebuild

Scope of Work
ҹɫÊÓƵ rebuilt 21.5 miles of single circuit 115 kV transmission line with 59 double dead ends and four backbone structures through 22 pulls (12 done by helicopter), and six outages while crossing I-95 and four railroad crossings.
Project Details
  • Demolished:
    • 551 TLF of wire
    • 213 H-Frames
    • 14 lattice towers
  • Installed 52 drilled piers, 40 pipe piles, 16 spread footers, and 345 direct embed foundations
  • Installed 32 temporary structures for outages
  • Set 193 multi-pole, 92 engineered, and 19 single-pole structures
  • Set 168 H-Frame, 16 three-pole dead end, and 13 single-pole aerial structures
  • Pulled 561 TLF ropes and wire
Lean, Innovative and Unique Project Solutions

To reduce equipment costs and eliminate particular safety hazards pertaining to the use of electrical cords, ҹɫÊÓƵ used battery-powered magnetic drills to drill out the transmission poles, either on the ground or after they were standing in the air, eliminating the use of generators and electrical cords.

No items found.

Our Offices
Corporate Headquarters
P.O. Box 1000
Pittsfield, ME 04967
207-487-3311
info@cianbro.com

Email Us

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.